If you don't want to calculate Cost, then there are 2 options.
- Keep separate Activity type, keep the Activity Price as Zero & use that activity type for those kinds of maintenance
- Configure separate Control key, don't select Cost tick box so that no cost will be calculated & use that for these maintenance activities.
I think, if cost gets calculated, TECO can't be done. So I hope, this will work.